History
The earliest electricity grids in the world emerged in the late 1800s and were primarily used to transport electricity short distances to power a limited set of technologies in large urban centers. As a case in point, shortly after inventing the first practical light bulb in 1879, Thomas Edison set to work developing the future electricity grid that would be required to power his invention, and in 1882 he installed the world’s first central steam generating plant in New York’s financial center that generated Direct Current (DC). At this time power was primarily used by businesses and others for lighting to attract customers.
Early electricity grids were also being developed closer to home. For instance, in 1881 the Niagara Falls Hydraulic Power and Manufacturing Company established a small hydro generation facility and provided some electricity to the village of Niagara Falls and the mills on the American side.1 Later in 1895 the Adam No. 1, the first large-scale Alternating Current (AC) electric generating plant in the world, was built in this area with contributions from legendary electricity forefathers such as George Westinghouse, Nikoli Tesla and others.2 This milestone is largely cited as being the beginning of modern grid operations as the use of AC current enabled the transfer of electricity for much farther distances than DC, with much lower line losses, and also enabled the use of more energy resources farther from load centers, such as hydroelectricity. The development of step-down power transformers to lower voltages around population centers also improved the safety of AC systems, which was the largest point of contention for proponents of DC (like Edison!).3 Today, the region is a major source of electricity for both Ontario and the New York State. In fact, 2,123 megawatts are produced at the Sir Adam Beck generating stations owned and operated by CEA member Ontario Power Generation (OPG). This is enough to power more than one million homes each year!4
As more appliances and electric motors were developed near the turn of the century that used electricity, demand for power increased beyond lighting, especially in applications such as street cars and industry.5 At this time many of the Canada’s power companies were small, privately held, and many went in and out of business.6 In the early 1900s as power use increased, hydropower stations became increasingly common, and some larger projects were commissioned at promising sites across the country that were farther from urban centers than was traditionally the case and used AC transmission and distribution systems to transfer electricity to population centers
Canada saw an emergence of large electricity, and particularly hydroelectricity projects in the first decades of the 20th century, and this was especially true in Western Canada where there was rapid economic and demographic expansion that required power. For example, Alberta’s first large-scale hydro project was commission by Calgary Power (now Electricity Canada member TransAlta) in 1911;7 and lower mainland BC’s first hydroelectric station opened at Buntzen Lake in 1903 with 27 kilometers of transmission to Vancouver.8
In the early 1900s there was a strong trend of transferring private power companies to municipal ownership particularly distribution systems. One of the most noteworthy events was the May 14, 1906, passing of legislation in Ontario that established the Hydro Electric Power Commission of Ontario (HEPCO), or later known as Ontario Hydro. Investment in generation was left to private parties, with Ontario Hydro having control over transmission in the province, and municipal control granted over distribution systems. Similar models were established across the country, and this set the stage for our modern grid. An example of this is the 1905 transfer of privately-owned Ottawa Light, Heat and Power to municipal ownership. This company would later become Hydro Ottawa and partner with HEPCO to be connected to the new Ontario provincial power grid.9
Our modern grid truly emerged after World War II as the Canadian economy boomed and increasing amounts of power were required. In many parts of the country, a combination of an inability to invest at the scale required (particularly in rural areas and smaller towns) and negative perceptions of incumbent power companies, pushed increasing levels of public investment in the power sector across the country. For instance, the Manitoba Hydro-Electric Board (MHEB), a precursor of Manitoba Hydro, was formed out of an amalgamation of other companies, guided by the belief the this would be the best way to provide the public with power.10
However, publicly owned power wasn’t the answer in all parts of Canada. In Alberta a 1948 plebiscite rejected public ownership of electric utilities by extremely narrow margins, with the ‘no’ side winning by 151 votes with a total of 279,831 cast.11 This was a problem as fewer than four percent of Alberta farms had access to power in 1945. Instead, Albertan farmers formed co-ops, also known as Rural Electrification Associations (REAs) in their districts to pool funding for electricity distribution infrastructure, with the Provincial government provided the rest of the money via loans. While the REAs owned the power distribution infrastructure the power companies in Alberta generated the electricity and performed maintenance. This model was extremely successful with 87% of rural Alberta having access to electricity by 1961, and elsewhere in Alberta the choice for privately procured power has existed to this day with the government of Alberta never owning or operating a utility company.12
Whichever ownership and investment path was taken, the Canadian electricity grid essentially evolved along this basic centralized grid model for much of the next half century. That is, large electricity generators, using transmission and distribution systems, were most efficiently and cost-effectively able to transport power to end users.
Key Messages
“To achieve least cost carbon reductions, greater inter-provincial and international coordination on transmissions system development is critical.”13 – NRCan
“Increased electrification and renewable contribution resulted in higher transmission benefits as transmission enhances resource adequacy during both normal conditions and extreme events in these scenarios.”14 – NRCan
“Allowing international transmission expansion provides $10 billion to $30 billion (2018 $US) of net value to the continental system between 2020 and 2050 (…)”.15 – NARIS Report
“Interregional and International Cooperation Can Provide Significant Net System Benefits Through 2050.” – NARIS Report
“Operational flexibility comes from transmission, storage, and flexible operation of all generator types.” – NARIS Report
Sources
1 Source: https://dr.library.brocku.ca/bitstream/handle/10464/2692/power.pdf
2 You can still visit this site today: https://www.google.com/maps/place/Adams+Power+Plant+Transformer+House/@43.0818475,-79.0450431,17z/data=!3m1!4b1!4m5!3m4!1s0x89d342f2bb115ad5:0xd83428df3370ed70!8m2!3d43.0821123!4d-79.0425137
5 Source: https://americanhistory.si.edu/powering/past/history1.htm
6 Based on the following sources:
- http://www.hydroquebec.com/history-electricity-in-quebec/timeline/toward-nationalization.html
- https://hydroottawa.com/en/about-us/our-company/our-history
- http://www.history.alberta.ca/energyheritage/energy/electricity/the-early-history-of-electricity-in-alberta/rural-electrification-in-alberta.aspx#page-2
- https://www.powerpioneers.com/bc-hydro-history/1929-1945/
8 Source: https://www.buntzenlake.ca/history/
9 Source: https://hydroottawa.com/en/about-us/our-company/our-history
10 Source: https://www.hydro.mb.ca/corporate/history/history_of_electric_power_book.pdf
12 Source: https://www.aeso.ca/aeso/training/guide-to-understanding-albertas-electricity-market/
14 Ibid